HVAC Upgrade Project Schedule

Regenstein Library HVAC Upgrade

Project Schedule by Phase
Project Schedule by Date

Project Schedule by Phase

HVAC renovation work will be done in phases. The anticipated schedule is as follows:

Phase Dates Notes
Ceiling tile removal 5/22/06-6/20/06
Completed
Duct cleaning 7/3/06-8/31/06
Work to be done when library is closed.
Minimal impact on library users.
Asbestos removal 7/6/06-8/31/06
Will be done in the Faculty Study Wing only.
See details.
Pipe demo 7/10/06-8/21/06
Will be done in the Faculty Study Wing only.
See details.
Flexible duct removal & replacement 7/17/06-10/16/06
Will proceed by floors, starting with the 5th
floor and continuing down to the 1st floor.

Work will occur 6:00 a.m. - 2:30 p.m.,
Monday-Friday, with minimal disruption to users.
Expect to see 2 or 3 technicians on ladders during
this phase.

Pipe, coil, baseboard & insulation 7/17/06-1/15/07
Will be done in the Faculty Study Wing only.
See details.
Replacement of mixing boxes 8/21/06-1/15/07

Project Schedule by Date

To see what work is scheduled for a specific time frame, click on the dates below: