Regenstein Library HVAC Upgrade
Project Schedule by
Phase
Project Schedule by Date
HVAC renovation work will be done in phases. The anticipated schedule is as follows:
| Phase | Dates | Notes |
| Ceiling tile removal | 5/22/06-6/20/06 |
Completed
|
| Duct cleaning | 7/3/06-8/31/06 |
Work to be done when library is
closed.
Minimal impact on library users. |
| Asbestos removal | 7/6/06-8/31/06 |
Will be done in the Faculty Study
Wing only.
See details. |
| Pipe demo | 7/10/06-8/21/06 |
Will be done in the Faculty Study
Wing only.
See details. |
| Flexible duct removal & replacement | 7/17/06-10/16/06 |
Will proceed by floors, starting with
the 5th
floor and continuing down to the 1st floor. Work will occur 6:00 a.m. - 2:30 p.m., |
Pipe, coil, baseboard & insulation | 7/17/06-1/15/07 |
Will be done in the Faculty Study
Wing only.
See details. |
| Replacement of mixing boxes | 8/21/06-1/15/07 |